Below is the list of items that are pending. We would like to submit the remainder as one submittal package.

Building 1 -
a.    Stair Treads: Details 6, 7 & 8/1A-9.3, A & B/1A-9.1
b.    Street Side Planter and Fountain Wall Cap: Details 4 & 5/1A-9.3, 1A-9.1
c.
Site Walls & Column Capitals:  B/1A-11.1
d.    Vehicle Gate Column Capitals:  Detail C/1A-11.1
e.    Pool Deck Column Capitals:  Detail 2 & 3 on1A-10.1
f.
Pool Deck Planter Curb:  Detail 5/1A-10.1
g.    Garage Parapet Column Capitals:  Note C.1 on 1A-6.7

2.    Building 2 –
a.
Main Entry Stair Treads: Detail 3/2A-9.4, 2/2A-9.4
b.    Unit Patio Sidewalk Stair Treads: Detail 7 & 8/2A-9.4
c.    Site Column Capitals:  9/2A-9.4

3.
Building 3 –
a.    Stair Treads: TA-0.3.1, TA-9.2
b.    Site Column Capitals:  TA-0.3.1 and TA-9.3
c.
Dumpster Enclosure Wall: TA-9.4

4.    Building 4 –
a.    Stair Treads: TA.0.3.2, TA-9.2
b.
Site Column Capitals:  TA-0.3.2 and TA-9.3
c.    Dumpster Enclosure Wall: TA-9.4

5.    Building 5 –
a.
Stair Treads: TA.0.3.2, TA-9.2
b.    Site Column Capitals:  TA-0.3.2 and TA-9.2
c.    Site Wall:  TA-3.1 and TA9.3
d.
Dumpster Enclosure Wall: TA-9.4

6.    Garden Courtyard –
a.    Site Column Capitals:  TA-9.1
                                                  i.
    Caps 2” thick
                                                ii.      Texture Smooth

7.    Building 6 –
a.
Building Veneer:  6A-6.1, Details 1 & 2/6A-6.2
                                                  i.      Material D2:  2” thick
b.    Stair Treads: 6A-0.3 and 6A-9.2
c.
Site Column Capitals:  6A0.3 and 8/6A-9.2
d.    Masonry Piers – 9/6A-9.2
                                                  i.      10” dia.
Ball finial on precast concrete sub base as specified in the detail.
e.    Pedestrian Gate Wall Cap:  2/6A-9.1
f.    Vehicular Entry column and wall cap: 1/6A-9.1
g.    Dumpster Enclosure Wall Cap: Details 3 & 5 on 6A-9.3
h.
Building 6 material texture and profiles to match as closely as possible to the existing Crescent House apartment community.
i.    A sample of your match to the existing crescent house apartment stone will be needed for Architect review and approval.

Categoria Engenharia e Manufatura
Subcategoria Desenhos em CAD
Do que você precisa? Criação a partir de um arquivo em outro formato ou esboço
Isso é um projeto ou uma posição de trabalho? Um projeto
Disponibilidade requerida Conforme necessário

Prazo de Entrega: Não estabelecido

Habilidades necessárias